San Leandro Boulevard East Bay Greenway Construction Timeline

When will the East Bay Greenway construction reach your stretch of San Leandro Boulevard? The official answer covers a 13-month window. Work began in October 2026 and is expected to wrap up by November 2027. The answer you can actually plan around comes much later, on a door hanger about five days before crews arrive on your block.

That gap tells you how this project works. Alameda CTC is not closing the corridor and rebuilding it all at once. Crews will work on no more than two blocks in a row at any given time. So for most of the next year, most of San Leandro Boulevard will look normal while a short section is torn up. Whether you're dealing with construction on any given week depends on where you live and park, not on the master schedule.

Agency staff, city officials and Bike East Bay marked the start on October 14 at the Boys and Girls Clubs of San Leandro, 2200 San Leandro Blvd. The Alameda CTC press release describes the club as sitting "directly on the future greenway." Bike East Bay puts this first package at 2.2 miles of new protected bikeway between Broadmoor Boulevard and East 14th Street. That's the first piece of a roughly 3.5-mile San Leandro route that will eventually continue down East 14th Street to Bayfair.

The calendar that matters is five days long

Alameda CTC sends notice in steps, and each step gets more specific as work gets closer:

  1. About two weeks out: Residents and businesses near the project get a notice by mail with project details, the work schedule and a contact for questions.
  2. About five days out: Door hangers go up on each block before work starts there. Alameda CTC also posts specific construction locations on roughly the same schedule.
  3. At least 72 hours out: No Parking signs go up where street parking will be temporarily unavailable. The agency says this gives people time to find other parking and avoid being towed.

The 72-hour signs matter most for anyone without a driveway, and for anyone who leaves a car parked on the street during a long weekend away. If you work from home on the boulevard or expect a delivery, you can also contact the outreach team directly. Alameda CTC asks residents and businesses to plan deliveries around the work. Its Community Outreach Team takes scheduling questions at [email protected] or 1-888-642-4555.

What an active work zone looks like on the boulevard

Inside an active work zone, San Leandro Boulevard drops to one lane in each direction. Crews can work 7 a.m. to 7 p.m., Monday through Friday. Weekend work from 8 a.m. to 7 p.m. is allowed if needed. The agency's FAQ says the work includes demolition, excavation, pavement markings and striping, so expect noise and dust near your block while crews are there.

Here's what Alameda CTC says will change while crews are on a block:

  • Traffic lanes shifted or closed
  • Some sidewalks temporarily closed or rerouted, with access to buildings kept open throughout
  • Temporary changes to parking and loading zones
  • Temporary bus stop closures or detours on AC Transit Route 28

The Route 28 item affects the most people beyond the boulevard itself. AC Transit runs the 28 from San Leandro BART to Hayward BART by way of Bay Fair BART, so a moved stop near San Leandro BART can change a regular commute. Bus riders get the same short notice as everyone else, because stop changes move with the two-block work zones.

Where the street changes most, according to the draft plans

The finished street will have protected bikeways, protected intersections, crosswalks with flashing beacons and pedestrian signals, new bus stops and bus loading islands, filled sidewalk gaps, new lighting, street trees and small plazas. For block-by-block detail, the best readable source is a set of plan sheets Alameda CTC showed San Leandro's Bicycle and Pedestrian Advisory Committee in November 2025. Every sheet is labeled "Draft for discussion purposes," so treat them as a guide to intent. They are not the final design.

Stretch of San Leandro Blvd What the November 2025 draft shows
East 14th to Rose Drive Bikeway protected by a buffer island
Coburn to Washington Corner protection islands for bikes, pedestrian refuge passages lined up with crosswalks, a designated garbage set-out area
Polar to Marina Sidewalk gaps closed, a right-turn slip lane removed, a new bus stop, gaps in side-street bike lanes closed
Harlan to Thornton Two right-turn slip lanes removed and a third shortened, new bus stops, a two-stage turn box for bikes, a new flashing beacon at the Thornton Street crosswalk
Parrott to Estudillo Bike ramps into the San Leandro BART station area, a shuttle stop, parking-protected bikeway, accessible parking spaces, a two-way bike connector on Estudillo

The same draft adds a connection at Siempre Verde Park. The park sits at Park Street and San Leandro Boulevard and has courts and play areas. Near the park, the plans add revised flashing beacons, a bulbout with landscaping, and a pedestrian hybrid beacon with a refuge island between the park and West Broadmoor.

The slip-lane removals are the change drivers will notice most. A slip lane lets cars take a right turn without stopping at the main intersection. Oaklandside reported in June that Bike East Bay was pushing to remove slip lanes in San Leandro because they make crossings more dangerous for people walking and biking. Between Polar and Thornton, the draft does that at several corners. If you drive the boulevard every day, those are the corners where your turns will feel different once work is done.

None of the current Alameda CTC materials say parking or travel lanes will be permanently removed on San Leandro Boulevard. Every lane and parking change described so far applies only during construction.

The finished version is a short drive north

You don't have to rely on drawings to see what's coming. Just past the city line, Oakland finished its own greenway segment on San Leandro Street, under the BART tracks, in June 2026. According to Oaklandside, it runs nearly a mile as a shared bike and pedestrian path from Seminary Avenue to 69th Avenue, then as a bike path from 69th to 75th. The same report lists a painted two-way bike path set apart from traffic by an unpaved strip, frequent street lamps, 70 new trees, heavy bollards at the start of each block to keep cars out, and new pedestrian signals at every intersection. The City of Oakland put the cost of that phase at about $4 million. Construction started in June 2023.

That stretch is useful for San Leandro residents for another reason. Oaklandside reported that Rob Prinz, advocacy director at Bike East Bay, rated it a better design than the first greenway piece near Coliseum BART, because its lighting points at the path instead of at the street and passing drivers. Each segment builds on what earlier ones got right, and San Leandro's is next in line.

The Oakland segment also explains why the greenway is being built on streets in the first place. The idea was first proposed in 2008 as a rail-to-trail conversion along the old Union Pacific tracks, similar to Berkeley's Ohlone Greenway. Oaklandside reported that Union Pacific still owns the tracks, which kept that plan from going forward. So the greenway is going into existing roadways, San Leandro Boulevard included, and existing roadways have to stay open for traffic, buses and deliveries while crews work. That's why this project moves two blocks at a time.

After the boulevard comes East 14th and Bayfair

The second San Leandro package covers East 14th Street, which is a Caltrans road, State Route 185. Alameda CTC's project page says that package will finish design in spring 2027. The same page also gives spring 2027 as the expected construction start for East 14th, so treat that start date as tentative until a notice shows up. Preliminary drawings for East 14th show bus loading islands between Bayfair Drive and Fairmont Drive and between 152nd Avenue and Hesperian and Bancroft, plus a beacon and median refuge in the second of those stretches.

The route ends at Bayfair, where the old mall is already being reused. San Leandro Next reported in June that Phase I of Speedway at Bayfair is converting 140,000 square feet of former mall space into R&D suites. Berkeley Yeast, Vantage Robotics, Reforge Robotics, Carrington College and San Joaquin Valley College are already there, and an Asian Health Services senior-care facility is planned for 2027. Once both packages are done, the greenway will connect downtown, San Leandro BART and the Bayfair site along one protected route.

If construction on your block of San Leandro Boulevard has you wondering how the finished street might affect your home's value or your plans to sell, I'm glad to walk the corridor with you and talk it through. Elic Suazo can help you schedule a consultation to explore your East Bay options.